鄂东长江公路大桥南塔承台大体积混凝土温度裂缝控制技术 被引量:1

Thermal Cracking Control Technology of the Mass Concrete of Pile Cap in South Main Tower of E-dong Yangtze River Bridge
下载PDF
导出
摘要 介绍了鄂东长江公路大桥南塔承台大体积混凝土夏季施工过程中裂缝控制措施,即在仿真计算的基础上,优化配合比,控制水泥出库温度,加冰拌和混凝土,及早通冷却水和现场温度监控等。从施工现场情况来,承台混凝土未出现温度裂缝。 On the basis of the simulation and calculation of thermal stresses, systematical temperature control measures were adopted to avoid thermal cracking during the construction of pile cap in south main tower of E-dong Yangtze River bridge, such as the optimization of mix proportion, the control of initial cement temperature, the concrete mixing with ice pieces, the early circulation of cooling water and the temperature monitoring in site. The results showed that the thermal cracking in practice may be efficiently prevented.
作者 卢勇 冯仲仁
出处 《建材世界》 2009年第5期37-40,共4页 The World of Building Materials
关键词 大体积混凝土 温度控制 绝热温升 冷却水 mass concrete temperature control adiabatic rise of temperature cooling water
  • 相关文献

参考文献3

二级参考文献3

共引文献108

同被引文献8

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部