摘要
某钽铌矿尾矿库即将库满停用,进入闭库程序。整治设计采取了沿坝轴线射水造混凝土防渗墙、翻修排水棱体和加设溢洪道消力池及钢筋混凝土护面等整治措施。经渗流及坝坡稳定等分析计算,表明设计采取的整治加固措施具有较好的效果,满足尾矿库安全要求。
The tailing pond of a certain Ta/Nb mine is full and going to be closed. To prevent environment pollution, the control measures of building concrete impervious wall along dam axial line, reconstructing drainage mound and adding spillway basin as well as paving with reinforced concrete are taken in design. It is indicated by calculation of seepage flow and analysis of slope stability that the tailing pond can meet the environmental protection requirement after the control and reinforcing measures are taken in design.
出处
《有色冶金设计与研究》
2009年第5期4-6,10,共4页
Nonferrous Metals Engineering & Research
关键词
尾矿库闭库
尾矿拦挡坝
渗流失稳
坝坡稳定
混凝土防渗墙
closure of tailing pond
detention dam
seepage flow
slope stability
concrete impervious wall