摘要
介绍了越南宣光水电站水轮发电机组的压水调相系统的设计,并针对现场的实际情况对其系统及电气流程所做的改进进行了总结和分析。重点说明现场试验所遇的问题,所得到的分析结果和解决处理情况。
The paper describes the design of unit phase modulation pressing water system of Tuyen Quang hydroelectric project, summarizes and analyzes the improvement of the system and electrical process in light of actual site conditions. It focuses on the problems met in field test, and analysis results and solutions.
出处
《西北水电》
2009年第5期61-66,共6页
Northwest Hydropower
关键词
水轮发电机组
压水系统
调相
水位信号计
控制流程
turbine-generator unit
pressing-water system
phase modulation
water level indicator
control process