整体升降脚手架与垂直运输施工机械的协调性 被引量:2

CONCORDANCE BETWEEN INTEGRATED LIFT SCAFFOLD AND VERTICAL TRANSPORT CONSTRUCTION MACHINERY
下载PDF
导出
摘要 一些整体升降脚手架施工方案在制定时,因未考虑大型垂直运输机械的平面位置及附墙杆立面安装尺寸等因素,造成机位布置不合理而导致碰撞。对此应根据垂直运输机械的附墙尺寸和平面选位原则,加强整体升降脚手架与垂直运输机械的协调性。 During the designing and making of construction program,because of negligence to take proper care of the placement of large-scale vertical transport construction machinery and the installation sizes of integrated lift scaffold,as a result,it is bound to have troubles and run into bumps and collisions.Therefore,the placements and installation sizes of them all should be carefully designed;and the concordance between integrated lift scaffold and vertical transport construction machinery would be enhanced,so that the construction security could be eventually guaranteed.
作者 李明
出处 《建筑技术》 北大核心 1998年第9期620-622,共3页 Architecture Technology
关键词 整体升降 脚手架 垂直运输机械 附墙杆 协调性 integrated lift,scaffold,vertical transport construction machinery,post attached to wall
  • 相关文献

同被引文献6

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部