摘要
某住宅工程3栋高层塔楼冬期施工中采用综合蓄热法,通过采用料场保温、现场集中搅拌、混凝土泵送等成套技术,简化了施工工艺,降低了成本,缩短了工期,使冬期施工仍然保证了接近常温的施工速度。
During winter construction of three highrise residential buildings,the comprehensive heat-saving method has been adopted.Through applications of :heat-retaining method,cast-in-place central mixing method,concrete pumping method,and whole set construction technology,as a result,their construction had been simplified,cost reduced,and working period shortened.Thus the speed rate of their winter constructions had approched that of the ordinary common temperature constructions.
出处
《建筑技术》
北大核心
1998年第10期685-686,共2页
Architecture Technology
关键词
综合蓄热法
泵送混凝土
高层住宅
冬期施工
winter construction,comprehensive heat-saving method,heat-retaining material,pumping concrete