防止超超临界机组汽动给水泵泵轴抱死调试技术及应用 被引量:2

Anti-jammed Commissioning Technology and Its Application of USC Turbine-Driving Feed Pump
原文传递
导出
摘要 在超临界及超超临界机组的调试过程中,汽动给水泵泵轴抱死事件屡有发生。一旦泵轴抱死,只能通过更换芯包解决,这直接影响了机组的正常运行及达标投产。分析了汽动给水泵泵轴抱死的主要原因,提出了在调试过程中避免泵轴抱死的技术措施,并将之应用于北仑三期工程超超临界机组汽泵调试过程,收到了良好的效果。 During commissioning of SC and USC units, jammed axle failures occurred to some turbine-driving feed pumps. Once the axle is jammed, it can only be replaced by a new core, which effects directly on unit' s start-up and normal operation. The paper analyses the main causes of the failures, and brings forward technical measures to prevent pump axle from jamming during commissioning. They were used in the course of turbine-driving feed pump commissioning in Guodian Beilun Phase Ⅲ USC units project with good results.
作者 王崇如 陶磊
出处 《电力建设》 2009年第11期60-62,共3页 Electric Power Construction
基金 国家工程项目(发改能源[2006]1391号)
关键词 超超临界机组 汽动给水泵 泵轴 防抱死 调试技术 uhra-supercritieal turbine-driving feed pump pump axle anti-jammed commissioning technology
  • 相关文献

参考文献8

二级参考文献6

  • 1申松林.超超临界1000MW等级火电机组电动给水泵容量配置分析[J].热机技术,2005(2):6-10. 被引量:4
  • 2-.建设项目经济评价方法与参数[M].中国计划出版社,1987..
  • 3Davidson D F,国外大电机,1992年
  • 4马芳礼,电厂热力系统节能分析原理,1992年
  • 5国家计划委员会,建设项目经济评价方法与参数,1987年
  • 6国华太仓2×600MW超临界机组8B汽动给水泵推力瓦损坏原因分析与处理对策[R].北京国华电力技术研究中心有限公司,2006.

共引文献24

同被引文献7

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部