摘要 朱仙庄矿位于安徽省淮北平原中部,设计生产能力为每年120万t,经过改造现年产200万t以上,许多设备严重制约产量的提升。为保证安全高效生产,对矿井供电质量、可靠性的要求也逐渐提高。被定为"双突"矿井后,电磁式保护已不能满足供电可靠性要求,遂决定对35 kV/6 kV变电所进行综合自动化改造。 Zhuxianzhuang mine is located in the central of Huaibei plain of Anhui province, which designed production capacity was 1.2 million tons per year. The annual production is more than 2 million tons after reforming and lots of devices constraints serious to enhance production. In order to ensure safe and efficient pro- duction, the requirements of quality and reliability of power supply is a gradual increasing. After the mine was designated as the "double process", the protection of electromagnetic can not meet the requirements of power supply reliability, so decided to reform the integrated automation of 35 kV/6 kV substation.
作者 王安斌
出处 《煤炭技术》 CAS 北大核心 2009年第11期28-30,共3页 Coal Technology
关键词 煤矿 35kV/6kV变电所 综合自动化改造 coal mine 35 kV/6 kV substation integrated automation reform
  • 相关文献

同被引文献4

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部