南水北调中线工程潮河段隧洞施工通风设计研究 被引量:2

Case Study on Design of Construction Ventilation System of Chaohe Tunnel on Central Route of South-to-North Water Transfer Project
下载PDF
导出
摘要 南水北调中线总干渠潮河段隧洞方案为2条平行圆形隧道,隧洞段长18.147 km,净间距26.6 m,设计洞径为12.1 m,采用2台土压平衡盾构机从进、出口相向掘进施工。由于隧洞较长,施工通风比较困难。根据隧洞布置形式、施工方案、主要污染源分析及隧洞施工作业环境的劳动卫生标准,研究计算了洞内需风量和风压,确定了通风方式和风机、风管的技术参数。 Chaohe tunnel on Central Route of South-to-North Water Transfer Project consists of twin parallel circular tubes. The tunnel is 18. 147km long. The clear spacing between the twin tubes is 26.6m. The designed diameter of the twin tubes is 12. lm. The twin tubes are to be bored by 4 EPB shield machines from the tunnel portals. Due to the long distance of the tunnel, it is difficult to execute construction ventilation. The required air flow and air pressure are calcu- lated and the required ventilation methods and ventilation parameters are determined on basis of the tunnel layouts, con- struction methods, major pollution sources and health standards of the working environment in the tunnel.
出处 《隧道建设》 2009年第5期499-502,509,共5页 Tunnel Construction
关键词 南水北调中线工程 施工通风 设计风量 设计风压 central route of south-to-north water transfer project ventilation designed air flow designed air pressure
  • 相关文献

参考文献5

二级参考文献7

  • 1赖涤全编著.隧道施工通风与除尘[M].北京:中国铁道出版社.1994.
  • 2DL/T5099—1999水利部水工隧道施工规范[S].
  • 3TB204—86铁道部标准铁路隧道施工规范[S].北京:中国铁道出版社,1988.
  • 4王在仁,林振球.秦岭隧道Ⅱ线出口段施工通风系统及测试分析.铁道工程学报,1998(10):178-183.
  • 5赖涤全.隧道施工通风与除尘.北京:中国铁道出版社.1994.
  • 6DL/T5099-1999.水利部水工隧道施工规范.
  • 7朱齐平,赖涤泉.秦岭隧道施工通风存在的问题及解决方案[J].铁道建筑技术,1999(4):27-29. 被引量:5

共引文献17

同被引文献12

引证文献2

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部