在大亚湾核电站核岛毗邻处进行工程爆破时,对施工爆破引起核岛的振动实施同步监测。通过测试结果的反馈,优化爆破方案。在确保大亚湾核电站安全运营的前提下,加快施工进度。
When construction blasting is performed near the nuclear island of Daya Bay nuclear power station, monitoring is carried out. By feeding back of testing results, blasting plan is optimized. In premise of assuring the safety of Daya Bay nuclear power station, the construction speed can be increased.
出处
《岩石力学与工程学报》
EI
CAS
CSCD
北大核心
1998年第5期594-598,共5页
Chinese Journal of Rock Mechanics and Engineering
关键词
核电站
核岛
振动监测
工程爆破
安全
nuclear power station, nuclear island, vibration test, acceleration