摘要
结合工程实例,着重介绍了斜拉索从旧索拆除到新索安装成型的更换工艺,得出了成桥索力满足设计要求的结论,指出此次斜拉索更换的顺利完成为以后的斜拉索更换积累了经验。
Combined with engineering example,the replacement technology from old inclined cable removal to new inclined cable installment confectioning was introduced critically,it concluded that cable tensions under dead loads satisfied with design requirement.It pointed out that the successful replacement of the inclined cable accumulated experience for future inclined cable replacement.
出处
《山西建筑》
2009年第34期306-307,共2页
Shanxi Architecture
关键词
斜拉索
千斤顶
索力
监测
inclined cable
lifting jack
cable tensions
monitoring