摘要
水布垭水电站运行初期,尾水河床形成冲坑和堆渣,抬高了尾水位,对发电有不利影响。清渣以后,发电效益明显增加。
In the early days after the Shuibuya Hydropower Plant was put into operation,the tailrace channel was filled up by a lot of debris and the tailrace water was raised,the energy output consequently reduced.After the debris were cleaned away,the energy output increased obviously.
出处
《湖北水力发电》
2009年第6期82-83,共2页
Hubei Water Power
关键词
水布垭水电站
尾水清渣
发电效益
Shuibuya Hydropower Plant
tailrace channel dredging
power generation benefits