运输时间不确定与上游可控提前期的供应链优化与协调 被引量:1

Optimization and Coordination of Supply Chains with Uncertain Transport Time and Controllable Upstream Lead Time
下载PDF
导出
摘要 研究由一个供应商与一个零售商组成的供应链系统。零售商面临确定连续需求,订货提前期由供应商可控生产(订购)时间与不确定运输时间组成。运输时间不确定所导致缺货费用由双方共同分摊。建立了分散决策与集中决策供应链模型,研究结果表明,集中决策模式下的供应链成本低于分散决策下的供应链成本,并且在集中决策模式下,最优决策是可控提前期不进行压缩。分散决策模式下,零售商承担缺货成本比例越高,博弈结果越接近集中决策模式下的结果。通过成本节约共享,可以实现供应链协调与整体优化。 In this paper, a disperse and a centralized decision-making model of supply chain are established, of which, the centralized decision-making model is shown to be more capable of reducing logistics cost. It is also found that, through cost saving sharing,the supply chain can be more integrated and coordinated.
出处 《物流技术》 2009年第12期175-178,187,共5页 Logistics Technology
基金 国家自然科学基金(70772077)
关键词 随机提前期 可控提前期 分散决策 集中决策 供应链协调 stochastic lead time controllable lead time disperse decision-making centralized decision-making supply chain coordination
  • 相关文献

参考文献23

  • 1Kaplan R. A dynamic inventory model with stochastiC lead times [J]. Management Science, 1970, 16 (7): 491-507.
  • 2Ehrhardt R. (s, S) Policies for a Dynamic Inventory Model with Stochastic Lead Times[J]. Operations Research, 1984, 32 (1): 121-132.
  • 3Liberatore M. Planning horizons for a stochastic lead-time inventory model [J]. Operations Research, 1977, 25 (6): 977-988.
  • 4Nevison C, Burstein M. The dynamic lot-size model with stochastic lead times [J].Management Science, 1984, 30 (1): 100-109.
  • 5Alp O, Erkip N, Gullu R. Optimal lot-sizing/vehicle-dispatching policies under stochastic lead times and stepwise fixed costs [J]. Operations Research, 2003, 51 (1): 160-166.
  • 6纪鹏程,宋士吉,吴澄.随机需求和提前期环境下的精确库存成本建模[J].计算机集成制造系统,2008,14(11):2129-2133. 被引量:7
  • 7Berman O, Kim E. Dynamic inventory strategies for profit maximization in a service facility with stochastic service, demand and lead time [J]. Mathematical Methods of Operations Research, 2004, 60(3): 497-521.
  • 8Chatfield D C, Kim J G, Harrison T P, Hayya J C. The Bullwhip Effect - Impact of stochastic lead time, information quality, and information sharing: A simulation study[J]. Production and Operations Management, 2004, 13 (4): 340-353.
  • 9Duc T T H, Luong H T, Kim Y D. A measure of the bullwhip effect in supply chains with stochastic lead time [J]. International Journal of Advanced Manufacturing Technology, 2008, 38(11-12): 1 201-1 212.
  • 10Chiu H N, Huang H L. A multi-echelon integrated JIT inventory model using the time buffer and emergency borrowing policies to deal with random delivery lead times [J]. International Journal of Production Research, 2003,41(13):2911-2931.

二级参考文献101

  • 1鲁其辉,朱道立,林正华.带有快速反应策略供应链系统的补偿策略研究[J].管理科学学报,2004,7(4):14-23. 被引量:30
  • 2贺政纲,帅斌,张杰.供应链企业在各种关系下的价格折扣方案设计[J].交通运输工程与信息学报,2006,4(3):80-86. 被引量:2
  • 3CHENG Feng, SETHI S P. A periodic review inventory model with demand influenced by promotion decisions[J]. Management Science, 1999, 45(11) :1510-1523.
  • 4AXSATER S. Using the deterministic EOQ formula in stochastic inventory control[J]. Management Science, 1996, 42(6):830-834.
  • 5BOOKBINDER J H, CAKANYILDIRIM M. Random lead times and expedited orders in (Q, r) inventory systems[J]. European Journal of Operational Research, 1999, 115(2) :300-313.
  • 6HADLEY S W. Safety inventory analysis: why and how[J]. Strategic Finance, 2004(9) :411-426.
  • 7MOHEBBI E. Supply interruptions in a lost-sales inventory system with random lead time[J]. Computers & Operations Research, 2003, 30(3):411-426.
  • 8JANAKIRAMAN G, ROUNDY R O. Lost-sales problems with stochastic lead times: convexity results for base-stock policies[J]. Operations Research, 2004, 52(5) :795-803.
  • 9SCHWARZ L B, WENG Z K. The design of a JIT supply chain:the effect of lead time uncertainty on safety stock[J]. Journal of Business Logistics, 2000, 21(2) :231-253.
  • 10JI P C, SONG S J, WU C. Infinitesimal dividing method:sole supplier inventory cost model with random lead times[C]// Proceedings of the 2006 International Conference on Machine Learning and Cybernetics. Washington, D. C. , USA: IEEE, 2006:231-253.

共引文献76

同被引文献14

  • 1马士华,杨文胜,李莉.基于二层规划的供应链多阶响应周期决策模型[J].管理科学学报,2004,7(5):31-39. 被引量:12
  • 2马辉,林晨.航班调度应急管理研究[J].中国民航学院学报,2005,23(5):11-14. 被引量:8
  • 3马士华,王福寿.时间价格敏感型需求下的供应链决策模式研究[J].中国管理科学,2006,14(3):13-19. 被引量:52
  • 4Thomas P R. Competitiveness through Total Cycle time[M]. New York : McGraw- Hill, Madidenhead, 1990.
  • 5Ehrhardt R. (s,S) Policies for a Dynamic Inventory Model with Stochastic Lead Times [J]. Operations Research, 1984,32 (1) :121-132.
  • 6Chiu H N, Huang H L. A multi-echelon integrated JIT inventory model using the time buffer and emergency borrowing policies to deal with random delivery lead times[J]. International Journal of Production Research, 2003,41(13) :2911-2931.
  • 7Liao C J, Shyu C H. Analytical determination of lead time with normal demand[J].International Journal of Operations and Production Management, 1991 ( 11 ) : 72-78.
  • 8BenDaya M,Raouf A. Inventory models involving lead time as a decision variable [J]. Journal of the Operational Research Society, 1994(45) : 579-582.
  • 9Ouyang L Y, Yen N C,Wu K S. Mixture inventory model with backorders and lost sales for variable lead time [J]. Journal of the Operational Research Society, 1996(47) :829-832.
  • 10Philip T,Evers. Filling customer orders from multiple locations: A comparison of pooling methods[J]. Journal of Business Logistics, 1999,20( 1 ) : 121-140.

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部