房地产项目进度迟延原因分析

Analysis of the Factors for the Delay of Schedule in Real Estate Projects
原文传递
导出
摘要 在房产开发项目中,普遍发生进度迟延。通过问卷调查分析了导致房地产项目进度迟延的27个主要因素的相对重要性,确定了影响房地产项目进度的最主要因素为:进度款支付困难、承包单位管理混乱、材料采购不到位、设计变更过多、建设单位决策缓慢,并给出相关建议。 Delay of schedule is common in real estate projects.A questionnaire survey is conducted to identify and evaluate the relative importance of the 27 significant factors contributing to delay in real estate projects.The results of the study reveals the main causes of delay includes:payment difficulties from agencies,poor contractor management,material procurement,design changing frequency and slow decision-making by construction units.Then gives some advices in order to minimize or avoid delay in real estate projects.
作者 张巍 陈浩
出处 《建筑经济》 2009年第12期36-39,共4页 Construction Economy
关键词 房地产项目 进度迟延因素 问卷调查 real estate project factors for the delay of schedule questionnaire
  • 相关文献

参考文献7

  • 1谭术魁.房地产项目管理[M].北京:机械工业出版社,2006.
  • 2[美]J.D.费雷姆.新项目管理[M].北京:世界图书出版社,2001.
  • 3张永福,钱磊.房地产开发中的项目管理[J].管理工程学报,2005,19(B10):255-257. 被引量:8
  • 4丁士昭.建设工程项目管理[M].北京:中国建筑工业出版社,2007.
  • 5萧鸣政.人员测评理论与方法[M].北京:中国劳动社会保障出版社.2006.
  • 6East, Hassanein, Melin. Evaluating factors that affectconstruc tion project duration[R]. United States:Construction Engineering Research Lab, 1992.
  • 7Ogunlana, Promkuntong, Jearkjirm.Construction delays in a fast-growing economy: comparing Thailand with other economies[J]. International Journal of Project Management, 1996,14( 1 ) :37-45.

共引文献30

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部