阐述了北江特大桥主墩基础双壁钢围堰加工、运输、沉放、封底施工过程,重点介绍了双壁钢围堰锚固体系的受力计算,以对类似工程受力计算参数选用提供查阅和参考。
This paper expatiates the construction process of double-walled steel cofferdam for the main bridge pier basis of Beijiang Bridge,include machining,transportation,immersion,cap end,and introduces mainly the force calculation of double-walled steel cofferdam anchorage system,providing reference for parameter selecting of force calculation in similar project.
出处
《山西建筑》
2009年第36期153-154,158,共3页
Shanxi Architecture
关键词
双壁钢围堰
加工
拼接
沉放
封底
double-walled steel cofferdam
machining
splicing
immersion
cap end