摘要
论述了特殊地质条件溶洞地区基础的设计,较详细阐述了桩基的选用原则,以及溶洞地区桩基的施工注意事项,解决了桩基施工中存在的问题,从而保证桩基施工质量。
Foundation design in special geological condition-karst cave area is discussed.The selection principle of pile foundation is elaborated in detail.In addition,matters deserving attentions in construction process are mentioned in order to resolve the questions encountered construction and ensure construction quality of pile foundation works.
出处
《山西建筑》
2010年第1期127-128,共2页
Shanxi Architecture
关键词
溶洞地区
桩基
冲孔灌注桩
施工
karst cave area
pile foundation
punched cast-in-situ pile
construction