摘要
以500kV双河变电站工程为例,论述了变压器施工技术,较系统地介绍了在施工中采取的措施和注意事项。
The on-site construction technology of large transformer is expounded, based on the 500kV Shuanghe Power Substation project. The measures and points for attention in the construction are introduced systematically here.
出处
《变压器》
北大核心
1998年第11期36-39,共4页
Transformer