摘要
在某110kV主变压器更换工程中,采用了新的施工方法使主变更换的停电时间缩短,停电时间由原来的120h缩短至16h,工程质量优质,安全性能好,取得了良好的效果,是主变在特定环境下新的施工工艺的成功尝试;为更换主变压器提供了施工新思路,对今后主变更换工艺的研究具有较高参考价值。
For a 110 kV main transformer replacement project,proposed new construction method shortened the power cuts of the main transformer from 120 hours to 16 hours.This method was experimented successfully which made the replacement work with excellent quality,safety and good effect.Provided new construction idea offers a high reference value for the main transformer replacement.
出处
《华中电力》
2009年第6期72-74,共3页
Central China Electric Power
关键词
施工方法
停电时间
主变更换
construction method
power cuts
main transformer replacement