摘要
介绍了冲积层表土段采用帷幕法施工,尤其是帷幕墙出现夹泥带时,采用高压旋喷桩封堵帷幕墙夹泥带,并采用井圈和喷射混凝土加固帷幕墙施工方法。认为该方法是相似地质条件下一种比较经济、有效和合理的施工方法。
This article presents an account about the use of curtain wall shaft sinking method for constructing the section of shaft through the alluvial top soil. In case loose material mixed with mud, sand and gravel comes out from behind the curtain wall, high pressure spiral jet-- grouting process is used to block the loose material from behind the curtain wall and crib rings and shotcrete is used to consolidate the curtain wall to help the shaft collar section pass through the alluvial layer. This is a comparatively cheaper, effective and rational shaft construction method for use under similar geological conditions.
出处
《中国煤炭》
北大核心
2009年第11期48-51,共4页
China Coal
关键词
竖井开凿
帷幕法
高压旋喷桩
shaft sinieing curtain wall
high-pressure spiral jet-grouting process