采用可用度理论的瓶颈设备前缓冲时间估计 被引量:2

Estimation of feeding time buffer size of bottleneck based on availability theory
下载PDF
导出
摘要 针对确定缓冲时间困难的问题,提出了一种基于可用度理论的缓冲时间估算方法,将瓶颈前的每道工序都看成独立的单部件可修系统,根据故障率和维修率由马尔可夫过程方法得到该工序的持续时间估计,从而估计出必需的缓冲时间.分别给出了瓶颈前有单个工序、多个工序串联、并联或混联时的缓冲时间估算公式,还提出了一种改进模糊概率PERT方法,对得到的缓冲时间进行可信度计算.基于在制品存储费用和概率风险损失给出了缓冲时间的最优化模型.仿真试验的结果表明,该方法得到的缓冲时间合理、可信. Aimed at the difficulty in determining the size of buffer properly, an availability theory based buffer sizing approach is proposed, in which each activity before the bottleneck is considered as a single repairable system, then the availability function infered by Markov process is used to estimate the processing time of the activities, and the proper buffer size can be calculated. The time buffer estimation formulas for different situa- tions are given respectively, in which the activities are in series, parallel or serials-parallel before bottleneck Moreover, an improved fuzzy probability PERT method is proposed to evaluate the credibility of the buffer size obtained. Finally, an optimization model is built to determine the optimal buffer size, taking inventory cost and total risk delay penalty as performance indicators. The results of simulation test indicate that the buffer size calculated by the proposed method is reasonable and believable.
出处 《哈尔滨工业大学学报》 EI CAS CSCD 北大核心 2009年第11期53-58,共6页 Journal of Harbin Institute of Technology
基金 国家高技术研究发展计划项目(2008AA04Z401) 哈尔滨电机厂生产计划系统开发项目
关键词 生产计划 缓冲时间 可用度理论 瓶颈 模糊概率PERT production plan time buffer availability theory bottleneck fuzzy probability PERT
  • 相关文献

参考文献10

  • 1GOLDRATT E M. Theory of Constraints [M]. New York: NorthRiver Press Inc, 1990.
  • 2陈杰,陈栋,马义中.基于约束理论的混流生产调度研究[J].中国机械工程,2007,18(20):2433-2439. 被引量:8
  • 3RADOVILSKY Z D. A quantitative approach to estimate the size of the time buffer in the theory of constraints [J]. International Journal of Production Economics, 1998, 55(2) :113 -119.
  • 4HUANG M G, CHANG P L, CHOU Y C. Buffer allocation in flow-shop-type production systems with general arrival and service patterns [J]. Computers & Operations Research, 2002, 29 (2) : 103 - 121.
  • 5LEE H W, AHN B Y. A queuing model for optimal control of partial buffer sharing in ATM [ J ]. Computers & Operations Research, 1998, 25(2) :113 - 126.
  • 6NEWBOLD R C. Project Management in the Fast Lane: Applying the Theory of Constraints [ M ]. New York: St. Lucie Press, 1998.
  • 7HERROELEN W, LEUS R. On the merits and pitfalls of critical chain scheduling [J]. Journal of Operations Management, 2001, 19(5) :559 -577.
  • 8TUKEL O I, ROM W O, EKSIOGLU S D. An investigation of buffer sizing techniques in critical chain scheduling[J]. European Journal of Operational Research, 2006, 172(2) :401 -416.
  • 9施文武,严洪森.知识化制造系统中生产瓶颈的分析方法[J].计算机集成制造系统,2006,12(2):271-279. 被引量:13
  • 10PERSONAA A, BATTINIA D, MANZINIB R, et al. Optimal safety stock levels of subassemblies and manufacturing components [J]. International Journal of Production Economics, 2007, 110( 1 -2) : 147 - 159.

二级参考文献31

  • 1李中阳,齐二石,安景玲.生产排程与模型构建研究[J].制造业自动化,2005,27(2):17-20. 被引量:12
  • 2MOSS H K,YU W B.Toward the estimation of bottleneck shiftiness in a manufacturing operation[J].Production and Inventory Management Journal,2000,40(2) :53-58.
  • 3ROSER C,NAKANO M,TANAKA M.Shifting bottleneck detection[A].Proceeedings of the 2002 Winter Simulation Conference[C].New York,NY,USA:IEEE,2002.1079 - 1086.
  • 4KUO C T,LIM J T,MEERKOV S M.Bottlenecks in serial production lines:a systems approach[A].Proceedings of the 35 th Conference on Decision and Control[C].Piscataway,NY,USA:IEEE,1996.2751-2756.
  • 5CHIANG S Y,KUO C T,MEERKOV S M.DT-bottleneeks in serial production lines:theory and application[J].IEEE Transaction Robotics and Automation,2000,5 (16):567 -580.
  • 6CHIANG S Y,KUO C T,MEERKOV S M.Bottlenecks inMarkovian production lines:a systems approach [J].IEEETransaction Robotics and Automation,1998,2 (14):352 - 359.
  • 7LI Jingshan,MEERKOV S M.Bottlenecks with respect to due -time performance in pull serial production lines[A].Proceedings of the 2000 IEEE International Conference on Robotics & Automation[C].Piscataway,NY,USA:Institute of Electrical and Electronics Engineers Inc.,2000.2635-2640.
  • 8HUANG Wenqi,YIN Aihua.An improved shifting bottleneck procedure for the job shop scheduling problem[J].Computers & Operations Research,2004,12(31):2093- 2110.
  • 9RAMUDHIN A,MARIER P.The generalized shifting bottle neck procedure [J].European Journal of Operational Research,1996,93(1):34-48.
  • 10Schragenhein E, Ronen B. Drum - Buffer- Rope Shop Floor Control[J].Production and Inventory Management Journal, 1990,3: 18-23.

共引文献18

同被引文献27

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部