摘要
简要介绍了在涪江三桥的施工测量中应用全站仪进行施工放样的作业方法,及时满足了墩柱、横梁、支撑等施工的需要,具有较高的放样精度和明显的作业效率。
Here we briefly report how to use the Electronic Total Station in measuring construction of 3rd bridge of Fujiang. The method of lofting with the Electronic Total Station timely meets the construction requirements of pier column, beam, support, and etc. , and has a relatively high lofting accuracy and an obvious working efficiency.
出处
《铁道建筑技术》
2009年第12期99-102,共4页
Railway Construction Technology
关键词
全站仪
施工测量
应用
electronic total station
construction measurement
application