摘要
本文描述了反应堆厂房蒸汽发生器吊装的施工条件与整个吊装施工过程。以及实践中的改进与创新,并分析了吊装中遇到的问题,提出了改进的建议。
The article described the lifting condition and the lifting process about the steam generator in the reactor building, explained the improvement and innovation method, analyzed the problem during the lifting process, and proposed the improvement suggestions.
出处
《核电工程与技术》
2009年第4期36-43,共8页
Nuclear Power Engineering and Technology
关键词
蒸汽发生器
吊装
恰希玛核电站
steam generator
lifting