摘要 在参考相关文献的基础上,结合工程实践,总结提出客运专线连续箱梁满堂支架设计计算的方法和步骤,并将之付诸哈大客专跨沈北大道现浇连续梁的工程实践,实践表明这套方法是经济可行的。 On the basis to refer to correlative literature, in the light of practice in project, the paper sums up and puts forward computational methods and steps of full hall scaffold design of continuous box girder for special railway line for passenger transpert, furthermore applies present methods and steps fo project practue o Ha - Da special railway line for passenger transport spanning Shen - Bei avenue. Practice proves this a suit of methods are economic and feasible.
作者 王晓明
出处 《北方交通》 2009年第12期46-49,共4页 Northern Communications
关键词 客运专线 现浇连续箱梁 满堂支架 设计计算 Special railway line for passenger transport Cast in place continuous box girder Full hall scaffold Calculation of design
  • 相关文献

参考文献12

二级参考文献9

共引文献4029

同被引文献6

引证文献1

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部