摘要
唐钢二期工程1260m3高炉上料皮带通廊结构吊装,采用三台大型吊车同时吊装。经过计算和精心施工取得了成功。
Carefully calculating and constructing,the feeding band conveyer corridor structure for 1260m 3 blast furnace in second project of Tangshan Iron and Steel Company was successfully hoisted as an integral with three large-scale hoists working simultaneously.
出处
《河北冶金》
1998年第2期113-117,共5页
Hebei Metallurgy
关键词
皮带通廊
吊车
吊装
高炉
band conveyer corridor hoist hoisting