基于提前期压缩的供应链博弈模型 被引量:5

A Study on Supply Chain Game Model Based on Lead-time Compression
下载PDF
导出
摘要 讨论基于提前期压缩的二阶供应链博弈问题,该供应链包括一个供应商和一个采购商。供应商采取批量分解方式向采购商供货。供应链成员通过提前期赶工的方式压缩提前期,降低成本。分别以供应商和采购商总成本最小化为目标,建立了由采购商为主方、供应商为从方的Stackelberg博弈模型。对提前期未赶工和提前期赶工2种情况下,采购商、供应商和系统三方的成本进行了对比,并对赶工后三方的成本节约情况进行比较分析。最后给出了算例和仿真,讨论了相关参数变化对采购商,供应商和系统三方总成本节约额的影响,并证明基于提前期压缩的博弈决策方式的有效性。 A problem of two-stage supply chain game model based on lead-time compression is discussed. The supply chain consists of one supplier and one buyer. The supplier adopts a lot-partitioning supplymethod. The members of the supply chain gain the lead-time compression by lead-time crashing. A Stackelberg game model is erected to gain the optimal cost of the buyer and the supplier. A comparison is givento compare the cost of the savings of the cost among analysis is given to show t uyer, supplier and the system with and without lead-time crashing, and the e third parties is analyzed, too. Finally, a numerical example and simulation effect of the variety of the parameters on the savings of the cost of the buyerthe supplier and total system. The validity of the method of game decision based on Lead-time compression is showed.
作者 吕芹 霍佳震
出处 《系统管理学报》 北大核心 2009年第6期625-630,共6页 Journal of Systems & Management
基金 国家自然科学基金资助项目(70772077)
关键词 提前期压缩 赶工成本 斯坦克尔伯格博弈 帕累托优化 lead-time compression crashing cost Stackelberg game Pareto improvement
  • 相关文献

参考文献17

  • 1Chu P,Yang K L,Chen P S. Improved inventory models with service level and lead time[J]. Computers Operations Research, 2005, 32: 285-296.
  • 2Tersine R J. Principles of Inventory and Materials Management. Prentice Hall, Englewood Cliffs[M]. 1994.
  • 3Liao C J, Shyu C H. A nanalytical determination of lead time with normal demand[J].International Journal of Operations & Production Management, 1991, 11(9): 72-78.
  • 4Ben Daya A M, Raouf A. Inventory models involving lead-time as decision variable [J]. Journal of the Operational Research Society, 1994, 45(5): 579-582.
  • 5Ouyang L Y, Yeh N C, Wu K S. Mixture inventory models with backorders and lost sales for variable lead time[J]. Journal of the Operational Research Society 1996, 47 : 829-832.
  • 6Moon I,Choi S. A note on lead time and distributional assumptions in continuous review inventory models [J]. Computers and Operations Research, 1998, 25 : 1007-1012.
  • 7Lan S P,Chu P,Chung K J,etal. A simple method to locate the optimal solution of inventory model with variable lead time [J]. Computer and Operations Research 1999, 26: 599-605.
  • 8Hariga M,Ben Daya A M. Some stochastic inventory models with deterministic variable lead time [J]. European Journal of Operational Research, 1999, 113: 42-51.
  • 9Hariga M, Ben Daya A M. Leadtime reduction in a stochastic inventory system with learning consideration [J]. International Journal of Production Research, 2003, 41(3): 571-579.
  • 10Chang H C,Ouyang L Y,Wu K S,Ho C H. Integrated vendor-buyer cooperative inventory models with controllablelead time and order cost reduction [J]. European Journal of Operatinat Research, 2006, 170: 481-495.

同被引文献51

  • 1梅晚霞,马士华.(Q,r)库存中的提前期压缩问题研究[J].中国管理科学,2007,15(6):73-77. 被引量:5
  • 2王亮,孙绍荣,李秀森,李世珣.基于Poisson分布需求的两级零售系统最优订货策略[J].上海理工大学学报,2005,27(3):229-233. 被引量:6
  • 3宋华明,马士华.供应链中提前期压缩的Pareto优化[J].控制与决策,2006,21(7):776-780. 被引量:11
  • 4宋华明,马士华.二阶段供应链中提前期压缩的影响与协调[J].管理科学学报,2007,10(1):46-53. 被引量:35
  • 5Sarmah S P,Acharya D,Goyal S K.Coordination and profit shari ng between a manufacturer and a buyer with target profit under credit option[J].European Journal of Operational Research,2007,182:1469-1478.
  • 6Weng Z Kevin.Modeling quantity discounts under general price-sensitive demand functions:Optimal policies and relationships[J].European Jo urnal of Operational Research,1995,86:300-314.
  • 7Teng Lefa.A comparison of two types of price discounts in shif ting consumers' attitudes and purchase intentions[J].Journal of Business Rese arch,2009,62:14-21.
  • 8Shin Hojung,Benton W C.A quantity discount approach to supply chai n coordination[J].European Journal of Operational Research,2007,180:601-61 6.
  • 9Perry, James H. Lead time management: Private and public sector practices[J]. International Journal of Purchasing and Materials Management, 1990, 26(1): 2-7.
  • 10Rohr S S, Correa H L. Time-based competitiveness in Brazil: Whys and hows[J]. International Journal of Operations & Production Management, 1998, 18(3): 233- 245.

引证文献5

二级引证文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部