摘要
以广州旺隆热电厂110MW热电联产机组为例,分析了热电联产机组电负荷与热负荷的耦合关系。在该机组协调控制策略中,增加了前馈回路,使机组既能很好地适应热负荷和电负荷的变化,达到在最大经济效益下的安全运行,并改善了机组重要参数的动态性能。
Taking the 110 MW cogeneration units in Guangzhou Wanglong Thermal Power Plant as an example,the coupling relationship between electric load and thermal load of cogeneration units has been analysed. In the coordinated control strategy of said units,a feed forward circuit has been added, making the unit can perfectly suit to variation of thermal load and electric load,achieving safe operation under maximum economic benefit, and the dynamic performance of important parameters concerning said units has been improved.
出处
《热力发电》
CAS
北大核心
2009年第12期88-91,共4页
Thermal Power Generation