摘要 通过对多项目管理瓶颈的分析,结合关键链方法,设置了瓶颈缓冲,建立了基于关键链方法的多项目管理,为多项目管理提供了一种新的管理方法.将基于关键链方法的多项目管理方法应用于并行多项目共享人力资源冲突管理,建立了基于遗传算法的多项目共享人力资源均衡模型,为缓解多项目共享人力资源供求矛盾提供了一种具体的量化管理方法,并进行了算例分析,证明了模型的有效性、实用性. The thesis analyses bottle neck of multi-project management,and designs multi-project management based on CCM by setup bottle neck buffer combining with CCM.So,it gives a new method for multi-project management.Multi-project management method based on CCM is applied to management with human resource sharing with multi-projects,and designs a multi-project sharing human resource balance model based on genetic algorithm.It proposes a very good statistical method for improving conflict of supply and demand of human resource sharing with multi-projects. Finally,we give an application to demonstrate its effectiveness.
作者 任秀 夏少刚
出处 《数学的实践与认识》 CSCD 北大核心 2009年第23期56-63,共8页 Mathematics in Practice and Theory
关键词 关键链方法 多项目管理 瓶颈缓冲 共享人力资源均衡 遗传算法 critical chain method multi-project management bottle neck buffer sharing human resource balance genetic algorithm
  • 相关文献

参考文献10

  • 1Goldratt E M. Critical Chain[M]. New York: The North River Press, 1997.
  • 2Leach L P. Critical chain project management improves project performance[J]. Project Management Journal, 1999,30(2):39- 51.
  • 3杨雪松,胡昊.基于关键链方法的多项目管理[J].工业工程与管理,2005,10(2):48-52. 被引量:63
  • 4郭庆军,赛云秀.关键链多项目进度管理分析[J].西安工业大学学报,2007,27(6):583-587. 被引量:15
  • 5Lee Jae-Kwan, Kim Yeong-Dae. Search heuristics for resource constrained project scheduling[J] . Journal of the Operational Research Society, 1996,47 (S) : 678-689.
  • 6Kurtulus I, Narula S C. Multi-project scheduling: Analysis of project performance[J]. IIE Transactions, 1985, 17(1):58-66.
  • 7王为新,李原.多项目资源均衡问题及其遗传算法[J].计算机应用研究,2006,23(12):46-47. 被引量:12
  • 8郭研,宁宣熙.利用遗传算法求解多项目资源平衡问题[J].系统工程理论与实践,2005,25(10):78-82. 被引量:34
  • 9Annika Zika-Viktorsson, Per Sundstro, Mats Engwall. Project overload: An exploratory study of work and management in multi-project settings[J ]. International Journal of Project Management, 2006, 24 (5) : 385-394.
  • 10雷英杰,张善文,李续武.MATLAB遗传算法工具箱及直用[M].西安:电子科技大学出版社,2005.

二级参考文献18

  • 1罗时朋,王乘,杨彪.基于浮动工时率的资源均衡问题研究[J].华中科技大学学报(自然科学版),2003,31(3):78-80. 被引量:3
  • 2[2]Goldratt EM.Critical Chain[M].New York.North River Press,1997.
  • 3[3]Patrick F S.Critical Chain and Risk Management-Protecting Project Value from Uneertainty[DB/OL].(2006-10-21)[2007-06-30].http.//www,focusdper-formance.com.
  • 4[7]Yeo K T,Ning J H.Integrating Supply Chain and Critical Chain Concepts in Engineer-procure-construct(EPC) Projects[J].International Journal of Project Management,2006,20(4):253.
  • 5Goldratt E M. Critical Chain [ M ]. New York: The North River Press, 1997.
  • 6Leach L P. Critical chain project management [ M]. London:Artech House Inc, 2000.
  • 7Rand G K. Critical chain: the theory of constraints applied to project management[J]. International Journal of Project Management, 2000, 18(3): 173-177.
  • 8Patrick F S. Critical Chain Scheduling and Buffer Management[ DB/OL] http ://www. focusdperformance, com, 2003 -04 -05.
  • 9Patrick F S. Critical Chain and Risk Management- Protecting Project Value from Uncertainty [ DB/OL ]. http :// www.focusdperformance, corn, 2004 - 10 - 21.
  • 10Steyn H. Project management application of the theory of constraints beyond critical chain scheduling [ J ]. International Journal of Project Management, 2002, 20: 75- 80.

共引文献108

同被引文献69

引证文献7

二级引证文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部