摘要 从材料与结构的角度分析了某大型客站混凝土结构地下风道施工中出现裂缝的原因并提出解决办法.表明在大型复杂工程的混凝土结构设计和施工中,在按照规范控制变形裂缝的同时,应考虑和注意施工过程中结构构件的受力状态的变化,对混凝土收缩裂缝控制也应涵盖施工全过程. Deformation cracks in the underground duct-line at a railway station project was analyzed from the perspective of materials and structures,and the solution was presented.It showed that when large and complex engineering and massive concrete structures was designed and constructed,the deformation should be controlled with normal rule.At the same time,the variation of the force of the architecture component should be paid attention,and the control method should be taken in the entire project.
出处 《仲恺农业工程学院学报》 CAS 2009年第4期36-39,共4页 Journal of Zhongkai University of Agriculture and Engineering
基金 仲恺农业工程学院校级自然科学研究基金(G2360261)资助项目
关键词 大型复杂工程 地下风道 混凝土 变形裂缝 large-scale and complex projects underground duct-line concrete deformation cracks
  • 相关文献

参考文献3

  • 1程文瀼,王铁成,颜德够.混凝土结构(上册)[M].北京:中国建筑工业出版社,2005.
  • 2赵英策,高鹏,徐嵩基.混凝土裂缝产生机理、分类与成因综述[J].工程与建设,2006,20(5):407-409. 被引量:9
  • 3中华人民共和国建设部.GB50204-2002混凝土结构工程施工质量验收规范[S].北京:中国建筑工业出版社,2002.