摘要
750 kV永登—白银同塔双回新建线路工程三标段跨越黄河段地形复杂,以高山大岭为主,沿线均为无人区,基本没有运输道路,施工材料和工具运输问题十分棘手。文章根据现场实际施工经验,详细阐述了多支点循环索道运输在输电线路中的应用,根据多支点循环运输索道布置情况,提出承载量参数计算,介绍了多支点循环索道安装与架设方法,有效解决施工材料的运输难题,保证了施工进度,为同类提供借鉴。
the third phase of 750kV Yongdeng- baiyin double- circuit transmission lines on the same tower crosses over complicated terrain, with high mountains and unpopulated areas, the transportation of constructing materials and implement is difficult without transporting road. The paper detailed expounds the application of multi - supports circulating ropeway transportation in transmission line according to the practical constructing experience, and based on the layout of ropeway, it proposes parameter calculating of skyline, as well as introduces installation and erecting method of the ropeway, the ropeway effectively solves the transportation problem of constructing materials and ensures the construction schedule.
出处
《青海电力》
2009年第4期41-45,共5页
Qinghai Electric Power
关键词
多支点
循环
索道
运输
输电线路
multi - support
circulation
ropeway
transportation
transmission line