摘要
为提高机组综合自动化水平,在300MW机组上进行了辅机故障快速减负荷性能试验。在分析试验过程及所解决的技术重点及难点问题的基础上,针对试验暴露出的诸如主蒸汽温度偏低等问题提出解决的办法。
In order to raise comprehensive automation level of generating units,performance test on running back of 300 MW generating unit resulted from auxiliary equipment fault was carried out.On the basis of the analysis of testing process and the solved key technical points and difficult problems,the measures for resolving the problems occurring during the test such as main steam temperature being on low side were suggested.
出处
《中国电力》
CSCD
北大核心
1998年第10期39-41,45,共4页
Electric Power
关键词
火力发电机组
辅机故障
减负荷性能试验
MW generating unit coordinate control system run back performance test