介绍了MBBR工艺在无锡芦村污水处理厂升级改造中的应用情况。该升级改造工程规模为20×104m3/d,分三期依次改造,主体改造工艺采用A2/O投加悬浮填料工艺(即MBBR工艺),出水水质稳定达到一级A排放标准。
The application of MBBR process to upgrading and reconstruction of Wuxi Lucun WWTP is introduced. This upgrading and reconstruction project with a scale of ×10^3m^3/d is performed in three phases. The main reconstruction process is A^2/O process with suspended carrier (MBBR process). The effluent quality can reach the first level A criteria of the national discharge standard.