期刊文献+

官地水电站岩锚梁开挖施工质量控制 被引量:2

Quality control in excavation of rack-anchored beam for Gongdi hydropower station
下载PDF
导出
摘要 岩锚梁是地下厂房开挖施工中难度最大、质量要求最高的部位,岩锚梁开挖成型的质量将直接影响到厂房岩壁吊车的运行安全。针对官地地下厂房以玄武岩为主、节理较发育、岩石较硬,采用了"岩锚梁分序开挖"和"岩台双光面爆破"的施工方法,取得了好的成型效果。 Rock-anchored beam,with the highest quality requirement,is the most difficult part in underground powerhouse excavation.The quality of the beam will directly affect the operation safety of the crane in the power house.According to the basalt dominated characteristic together with its developed joints and hard rock conditions of Gongdi underground powerhouse,Sub-sequence Excavation Method and Both Smooth Rock Side Blasting Method are applied and have significant molding effect.
出处 《东北水利水电》 2010年第1期28-30,45,共4页 Water Resources & Hydropower of Northeast China
关键词 地下厂房 岩锚梁开挖 施工方法 官地水电站 Underground powerhouse rock-anchored beam excavation operation method Gongdi hydropower station
  • 相关文献

参考文献2

共引文献1

同被引文献12

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部