摘要
通过对牛栏沟水电站导流程序的合理划分,提出了非汛期利用时段,为实现总工期目标,打下了坚实基础。使用导流手段缓解工期紧张矛盾,是水电工程探索的课题。
The design concept of the construction diversion for the project of Niulangou Hydropower Station is briefly described herein ; in which the impacts from the characteristics and difficulties of the diversion on the construction schedule is also expatiated. The available period of the non-flood-season is then presented through the reasonable division of the diversion process, so as to make a better basis for realizing the object of the general construction schedule. On the whole, it is really a subject to be further studied for alleviating the contradiction from the limited construction period with the method of water diversion.
出处
《水利水电技术》
CSCD
北大核心
2010年第1期61-63,70,共4页
Water Resources and Hydropower Engineering
关键词
施工导流
导流标准
导流明渠
围堰
枯水基坑
牛栏沟水电站
construction diversion
standard of diversion
open-channel of diversion
construction cofferdam
foundation pit of low water
Niulangou Hydropower Station