摘要
主要介绍了工程量清单计价与传统定额计价的区别,从工程项目设计阶段、招标阶段、施工阶段、竣工结算阶段等方面,对工程量清单计价模式下的造价控制进行了阐述,以进一步完善工程量清单计价管理办法。
The differentiations between engineering quantity list valuation and traditional fixed quota valuation are mainly introduced.From design stage,bid invitation stage,construction stage,completion budget stage and other aspects of engineering project cost control under engineering bill pricing mode is discussed,in order to further perfect the valuation management method based upon engineering quantity list.
出处
《山西建筑》
2010年第4期257-257,336,共2页
Shanxi Architecture
关键词
工程量清单计价
工程项目
造价控制
engineering quantity list valuation
engineering project
cost control