预偏补偿悬臂端位移在钢桁架拱桥跨中无应力合拢施工中的应用 被引量:2

Application of pre-deviation compensation for cantilever end displacement in non-stress closure construction at mid-span steel truss arch bridge
下载PDF
导出
摘要 重庆朝天门长江大桥是目前世界上最大跨度的拱桥,设计无应力跨径为190 m+552 m+190 m,从边支点向跨中悬臂安装。采取预偏施工技术,调整边、中支点高差及位移,补偿合拢口高差及位移,成功实现桁拱跨中无应力合拢,可供类似工程施工参考。 Chongqing Chaotianmen Yangtze River Bridge is the largest arch bridge in span currently in the world with a design non-stress span of 190 m+552 m+190 m, installed from side bearing point to mid-span cantilever. This paper uses pre-deviation construction technique to successfully achieve non-stress closure at the mid-span by adjusting the elevation difference and displacement between side and middle bearing points to compensate the elevation difference and displacement at the closure opening, serving as a reference for the similar engineering construction.
出处 《水运工程》 北大核心 2010年第1期117-121,共5页 Port & Waterway Engineering
关键词 钢桁架拱桥 预偏补偿法 无应力合拢 steel truss arch bridge pre-deviation compensation method non-stress closure
  • 相关文献

参考文献3

  • 1TB10203-2002,铁路桥涵施工技术规范[S].
  • 2JTJ 025-1986,公路桥涵钢结构及木结构设计规范[S].
  • 3向中富.重庆朝天门长江大桥施工控制分析报告[R].重庆:重庆交通大学,2006.

共引文献26

同被引文献13

引证文献2

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部