期刊文献+

高温管道冷紧施工中冷紧口焊接组对质量的控制 被引量:1

Cold Tightening Assembly Quality Control in High Temperature Pipeline Construction
下载PDF
导出
摘要 高温蒸汽管道的补偿器附近要设置冷紧口,但有关设计规范只规定冷紧口位置应设在便于施工(如靠近平台、梁柱等)和管道弯矩较小处,因此冷紧口位置的设计常会出现不合理的情况,导致冷紧时冷紧口难以组对焊接。文章结合某石化公司中压蒸汽管道冷紧施工的实际,阐述了通过冷紧口移位来解决冷紧口组对焊接难的问题。结果表明:按原设计冷紧口位置进行施工,组对一道冷紧口需要4个工日,而移位后仅用不到2个工日。 Cold tightening joint should be set up near the compensator of high temperature steam pipeline, but the relevant design code only stipulates that cold tightening joint should be positioned in the places favourable to welding and operation. Therefore, the design of cold tightening joint position may be unreasonable so as to bring difficulty to cold tightening assembly. Based on the cold tightening construction of the medium pressure steam pipeline owned by a petrochemical company, this paper expatiates on the method of shifting cold tightening joint to overcome welding difficulty. The results show that the butt welding time for one cold tightening joint decreases from 4 working days with the original construction method to 2 working days with the shifting method.
出处 《石油工程建设》 2010年第1期51-53,共3页 Petroleum Engineering Construction
关键词 高温管道 冷紧口 组对 移位 焊接 high temperature pipeline cold tightening joint assembly shift welding
  • 相关文献

参考文献2

  • 1GB50235-1997.工业金属管道工程施工及验收规范[S].[S].,..
  • 2SH3501-2002.石油化工有毒、可燃介质管道工程施工验收规范[S].

共引文献17

同被引文献2

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部