结合朝阳寺隧道下穿渝邻高速段地质情况,介绍了超浅埋大断面隧道的施工方案,重点阐述了超前大管棚和微台阶法的施工方法及监控量测内容,并进行了效果评价,为今后类似的工程施工积累了经验。
Combined with the geological situation of Chaoyangsi tunnel under Yu-Lin express highway section,the advanced shallow large section tunnel construction planning was introduced,the construction methods and monitoring measuring contents of advanced large pipe shed and micro step method were illustrated critically.The effect was evaluated so as to accumulate experience for future similar engineering construction.
出处
《山西建筑》
2010年第7期299-301,共3页
Shanxi Architecture
关键词
隧道
超前大管棚
微台阶法
监控量测
tunnel
advanced large pipe shed
micro step method
monitoring measurement