吸收塔是火电厂烟气脱硫装置中的关键性设备,采用倒装法施工,由于在降低费用、缩短工期、减少高空作业量、不受场地限制等方面具有显著的优点,因而在吸收塔的施工技术中被广泛采用,文中对其倒装法施工工艺、质量控制及注意事项作了介绍。
The absorber is a thermal power plant flue gas desulfurization devices,the key device,using flip-chip method of construction,due to lower costs,shorten schedules,reduce the amount of high-altitude operations are not subject to site constraints and so has significant advantages,thus absorption tower construction technology has been widely adopted,the text introduces its construction process,quality control and precautions.
出处
《安徽电力》
2009年第4期32-35,共4页
Anhui Electric Power
关键词
火力发电厂
烟气脱硫
装置
吸收塔
倒装法
thermal power plant
flue gas desulfurization
device
absorber
flip chip