发电机在增容改造前的温升试验 被引量:4

Temperature-Rise Test of Motors Before Capacity-Increased and Reconstruction
下载PDF
导出
摘要 介绍发电机温升试验方法,指出温升试验时需要负荷稳定和热稳定,并说明温度测试方法,计算方法和温度修正等。通过以一台额定容量150MW水轮发电机的温升试验为例,测试该发电机各部件的温度,并对额定负荷温升进行了推算。最后,通过该台机组的温升试验,推算出发电机增容改造的绕组电流和容量。 This paper introduces the temperature-rise test method of generator, and points out that load and thermal stability are necessary for the temperature-rise test. The measurement method, calculation method and modification of temperature are explained. Through temperature-rise test of a 150MW water turbogenerator, the temperature of various components were measured and the rated load temperature-rise was extrapolated. At last, through the temperature-rise test of this units, the winding current and capacity of the generator after capacity-increased and reconstruction were derived.
出处 《防爆电机》 2010年第1期30-33,共4页 Explosion-proof Electric Machine
关键词 温升试验 转子温度 定子温度 增容改造 Temperature-rise test rotor temperature stator temperature capacityincreased and reconstruction
  • 相关文献

参考文献4

二级参考文献1

  • 1GB/T1029-93,三相同步电机试验方法[S].

共引文献5

同被引文献12

引证文献4

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部