摘要 本文以龙岩市商会大厦桩基工程施工为背景,通过对某桩基事故的处理与分析,介绍了冲孔灌注桩工艺在溶洞、裂隙发育地区施工过程中,由于地质情况复杂或者施工控制不当等情形下造成的问题所采用施工处理措施。 In this paper, the basis of Longyan City Chamber of Commerce Building, construction process as the background of a pile foundation through incident handling and analysis, introduced the pile punching process in cavities in fractured areas in the con- struction process, due to the complex geological conditions or the Construction Control improper design changes and other factors which should be used in cases where the shift, grouting reinforcement weak areas of construction programs; as well as through the pile and pile cap stress analysis stress analysis to introduce the changes and the instability caused by Shouli Bu are issues such as analysis.
作者 熊锋 彭小燕
出处 《福建建筑》 2010年第2期77-79,84,共4页 Fujian Architecture & Construction
关键词 冲孔灌注桩 溶洞 裂隙 移位 注浆加固 受力分析 Punching pile Cave Fissure Shift Grouting Force analysis
  • 相关文献

参考文献4

  • 1JGJ 94-2008,建筑桩基技术规范[S].
  • 2孔思丽主编.工程地质学[M].重庆:重庆大学出版社,2003.
  • 3陈晓平 陈书申.土力学与地基基础[M].武汉:武汉工业大学出版社,1997.4-8.
  • 4赵明华主编.基础工程[M].北京:高等教育出版社,2005.

共引文献1151

同被引文献2

引证文献2

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部