摘要
结合武汉三环线某小箱梁预制场的实例,从各方面阐述了梁场的选址、布置及规划、工装设备的配备,并总结了一些在实施过程中的施工经验,在某些方面具有一定的参考意义。
By combining with the example of some small box girder prestressed field of Three-ring line in Wuhan, the paper illustrates the ad- dress selection of the beam field, the layout, the planning and configuration of the equipment, and sums up some construction experience in implementation process, so it has the reference significance for some aspect.
出处
《山西建筑》
2010年第8期164-164,196,共2页
Shanxi Architecture
关键词
预制场
布置
规划
prestressed field, layout, planning