摘要
介绍了梯级水电站自动发电控制的原理及其运行方式,针对三峡梯级水电站的特点和梯级自动发电控制运行的要求,提出了枢纽、母线二层负荷分配的算法。
The working principle and operational mode of AGC in cascade hydropower stations are the characters of Three Gorges cascade hydropower stations and the operation requirement of AGC, described. Based on the arithmetic about load distribution both on hinge level and on bus level is proposed.
出处
《水电与新能源》
2010年第1期9-12,共4页
Hydropower and New Energy
关键词
梯级调度
AGC控制
闭环
dispatching of cascade hydropower stations
automatic generation control(AGC)
close loop