变电站■接线中母线电压互感器缺省的设计及研究

DESIGN OF POTENTIAL TRANSFORMER OMITTED AT BUSBAR IN BREAKER-AND-A-HALF CONFIGURATION SUBSTATION
下载PDF
导出
摘要 在11/2主接线的变电站中,当母线保护不采用母线电压信号时,提出了不设母线电压互感器,可节省两套母线电压互感器及其避雷器。如果需要母线电压测量值,则可通过可编程控制器控制的切换开关来实现,取自于与母线相联的进出线或变压器的电压互感器二次回路。 In breaker-and-a-half configuration substation. it is raised not to install potential transformer at bus because the bus protection doesn't adopt the signal of bus voltage. So two sets of potential transformers at bus and their arresters can be omitted. If necessary. the measured value of bus voltage can be obtained through switching from the secondary measuring circuit of potential transformer linked to in-or-out line or transformer connected to the bus. Voltage switching can be realized by a set of switch device developed with programmable controller.
出处 《电力系统自动化》 EI CSCD 北大核心 1998年第11期65-66,共2页 Automation of Electric Power Systems
关键词 变电站 接线 母线 电压互感器 电气接线 breaker-and-a-half configuration potential transformer substation voltage measurement
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部