摘要
小湾水电站导流底孔下游侧布置弧型工作门,弧门设置充压水封装置,给弧门结构件的吊装增加了难度,施工单位根据现场施工条件,制定出切实可行的吊装方案,顺利完成了弧门结构件的吊装,为后续弧门结构件的吊装积累了经验。
In the Xiaowan hydropower station, the low diversion tunnel is designed of a are gate at its downstream side, the pressured seal of the are gate makes hoisting and installation of the gate difficult. With a practical scheme the construction successfully set the gate into position, contributing good experience to installation of other gates in future.
出处
《青海电力》
2009年第A01期46-50,共5页
Qinghai Electric Power
关键词
小湾水电站
导流底孔
弧门
吊装
Xiaowan hydropower station
low diversion tunnel
arc gate
hoisting and installation