龙马水电站导流洞进口渐变段优化设计 被引量:1

The Optimized Design of the Diversion Tunnel Intake Transition Section for Construction of the Longma Hydropower Project
下载PDF
导出
摘要 龙马水电站导流洞渐变段由于施工条件限制,结合施工工期、工程结构安全等方面进行系统研究,调整渐变段结构体型,由原浅埋式优化为明洞。为工程的顺利建设和按期投产创造了条件,工程经济效益明显。2007年3月导流洞下闸封堵期间,在93m外水水头直接作用下,渐变段结构安全可靠,没有出现结构破坏和渗漏情况。 The structural configuradon of the transition section of the diversion tunnel for construction of the Longma hydropower project was readjusted and changed into an open cut tunnel from a deeply buffed tunnel after optimization in view of its restricted construction conditions, construction schedule and structural safety, which created favorable conditions for successful completion and commercial operation of the project on schedule, thus bringing about significant economic benefits. The transition structure proved safe and reliable and neither damage nor leakage was found under direct action of an external water head as high as 93m during gate closing and plugging of the ttmnel in March, 2003.
出处 《云南水力发电》 2010年第1期15-19,56,共6页 Yunnan Water Power
关键词 龙马水电站 渐变段 外水作用 渗漏要求 经济效益 Longma Hydropower Plant transition section external water head effect leakage requirement economic benefits
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部