法国马尔帕塞拱坝在1959年2月溃决失事,死亡失踪500余人,财产损失300亿法朗,迄今已40年,经过世界各国许多坝工和地质专家调查研究,法院审判,但对事故原因始终没有得到一致意见,也没有确定谁应负责。最近阅读汝乃华、姜忠胜编著《大坝事故与安全——拱...
Abstract For Malpassit arch dam, a wrong type of dam was selected on a wrong dam site. The thickness of an arch dam, its stresses and stability, and the foundation treatment must as a whole conform to the geologieal and topographic conditions of the dam site. The design should be worked out in accordance with the conventional regulations and subject to appraisals by experts from outside.