中厚板热轧生产调度优化方法 被引量:1

Optimization Method for Plate Hot Rolling Production Scheduling
下载PDF
导出
摘要 中厚板热轧生产调度,是一个有优先约束、等待时间和缓冲容量有限的单机调度问题.用AON(Activity-on-node)网络对问题进行描述,提出并证明了面向单机调度问题的AON网络平衡定理,根据平衡定理,建立了以轧机利用率最大为优化目标的非线性约束优化数学模型,并利用优化软件LINGO进行求解.计算实例表明,所提出的数学优化方法,与现有的启发式方法相比,能够获得更好的优化目标,所得到的生产调度方案,生产节奏稳定,更有利于组织生产. Scheduling steel plate hot rolling is a typical single-machine scheduling problem subject to multiple constraints including precedence constraints and limited waiting time and finite buffer capacity. To describe the steel plate hot rolling scheduling problem with an AON (Activity-on-node) network, an equilibrium principle is formulated for single-machine scheduling problems on the AON networks. Subsequently, a nonlinear constrained optimization model is built for steel plate hot rolling scheduling problems, which maximizes utilization of the rolling mill and is solved by software LINGO. Numerical computations indicate that the hot rolling scheduling method is more effective than the heuristic methods available in reaching optimal production schedules that may significantly improve production stability and efficiency.
出处 《自动化学报》 EI CSCD 北大核心 2010年第2期282-288,共7页 Acta Automatica Sinica
基金 解放军总装备部武器装备预研重点基金项目(9140A18010207LN0101)资助~~
关键词 中厚板热轧 AON (Activity-on-node)网络 非线性约束优化 单机调度 Plate hot rolling AON (Activity-on-node) network nonlinear constrained optimization single-machine scheduling
  • 相关文献

参考文献6

二级参考文献36

  • 1白埃民,郝付国,张进之.综合等负荷函数法在中板生产中的应用[J].钢铁,1993,28(4):35-39. 被引量:10
  • 2赵玉芳,唐立新.极小化最大完工时间的单机连续型批调度问题[J].自动化学报,2006,32(5):730-737. 被引量:18
  • 3Samways N L. Modernization at Lukens Steel: past, present and future[J], lron and Steel Engineer, 1987,64(8):23-29.
  • 4Murphy T M. On-line plate mill process control computer replacement[J ]. Iron and Steel Engineer, 1993,68 (6): 23- 24.
  • 5Bernard F. Optimum cornputer control of a plate mill[J].Iron and Steel Engineer, 1980,57( 11 ):58- 64.
  • 6Evans R D. Plate mill automation at U. S. Steel, Gary Works[J]. Iron and Steel Engineer, 1993,68(3) :44 - 47.
  • 7Nagahisa L. Advanced automation on the new plate mill at Mizushima Works[J ]. Iron and Steel Engineer, 1978, 55(12):34-40.
  • 8Print H. Process simulation by a compmer model[J ]. Steel Times, 1980,208(7) :483 - 488.
  • 9Fenstermaker L J. Low-cost plate mill improvements[J ].Steel Times, 1986,214(6) :287 - 288.
  • 10周宝剑.[D].北京:北京理工大学自动控制系,2001.

共引文献39

同被引文献14

  • 1Gupta J N D. Two-stage hybrid flow shop scheduling problem [J]. Journal of Operational Research Society, 1988, 39 (4) : 359-364.
  • 2Witt A. Simple heuristics for scheduling with limited inter-mediate storage[J]. Computers & Operations Research, 2007, 34(8) : 2293-2309.
  • 3Norman B A. Scheduling flowshops with finite buffers and sequence-dependent setup tinles[J]. Computers & Industrial Engineering, 1999, 36( 1 ) : 163-177.
  • 4Nowicki E. The permutation flow shop with buffers: a tabu search approach [J]. European Journal of Operational Research, 1999, 116(2):205-19.
  • 5Qian B, Wang L. An effective hybrid DE-based algorithm for multi-objective flow shop scheduling with limited buffers [J]. Computer & Operations Research, 2009,36 (4) : 209-233.
  • 6Ruiz R. The hybrid flow shop scheduling problem[ J]. European Journal of Operational Research, 2010, 205(3) :1-18.
  • 7Tang L, Xuan H. Lagrange relaxation algorithms for real- time hybrid flow shop scheduling with finite intermediate buffers [J].Journal of the Operational Research Society, 2006, 57(2) :316-324.
  • 8Sawik T. An exact approach for batch scheduling in flexible flow lines with limited intermediate buffers [ J ]. Mathematical and Computer Modelling, 2002, 36( 1 ) :461-471.
  • 9Akrami B, Karimi B. Two metaheuristic methods for the common cycle economic lot sizing and scheduling in flexible flow shops with limited intermediate buffers: the finite hori- zon case[J]. Applied Mathematics and Computation, 2006, 183 (2) :634-645.
  • 10Khosla I. The scheduling problem where multiple machines compete for a common local buffer[ J]. European Journal of Operational Research, 1995, 84 (3) :330-342.

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部