摘要
在9.2 km长廊胶带输送机的安装过程中,成功地解决了施工现场场地和道路差的难题。特别是实施跨海河桥的钢结构牵引方案,顺利地安装了大跨度钢栈桥,解决了双曲线长跨度输送机运行中的跑偏问题,确保了设备的正常运转和良好的港区环境。
During the process of installing 9.2 km corridor belt conveyor, successfully solved the poor construction sites and road problems. Especially for the traction program of steel structure in Haihe-crossing Bridge, a large-span steel trestle was smoothly installed to solve the rubber belt run-out in hyperbolic long-span conveyer, to ensure a smooth operation for the equipment and a well environment for the port.
出处
《中国港湾建设》
北大核心
2010年第1期65-68,共4页
China Harbour Engineering
关键词
长廊输送机
大跨度钢栈桥
安装施工
corridor conveyor
large-spansteeltrestle
installation and construction