摘要 小湾水电站枢纽坝高达292m,泄洪流量大,泄洪能量高,雾化问题突出。因此泄洪雾化是枢纽泄洪消能研究专题中一个重要部分。通过大比尺枢纽整体模型,进行小湾雾化问题研究,较可靠地提出量化的雨强、雨区分布等资料,并对雾化防治问题提出建议,可供设计研究参考使用。 Atomization of the Xiaowan Hydropower Project is a protuberant problem due to its 292m high dam, large flood discharge and high flood discharging energy. Therefore the study of flood discharge atomization is an important part of the flood discharge energy dissipation monographic study of the project complex. The study of atomization problem for the Xiaowan project by means of a large scale entire complex model can provide such reliable quantified data as distribution of rainfall intensities and rainfall zones, and make proposals for prevention and remedy of atomization, which can be applide to both design and study.
作者 陈惠玲
出处 《云南水力发电》 1998年第4期51-55,共5页 Yunnan Water Power
基金 "八五"国家科技攻关项目
关键词 小湾水电站 泄洪雾化 泄洪消能 Xiaowan Hydropower Project flood discharge atomization rainfall intensity rainfall zone visiblility
  • 相关文献

参考文献2

  • 1姜信和,张任.挑射水股空中掺气扩散特性的初步研究[J]水利学报,1984(07).
  • 2[美]赫斯(Hess,W·N·) 主编,王昂生,徐华英.人工影响天气和气候[M]科学出版社,1985.

同被引文献98

引证文献8

二级引证文献30

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部