唐口煤矿主井井筒注浆堵水方案及应用 被引量:15

Grouting and Water Sealing Plan and Application to Main Shaft in Tangkou Coal Mine
下载PDF
导出
摘要 针对唐口煤矿地质条件复杂、涌水量较大等特点,提出了采用单液水泥浆和黏土水泥浆等2种浆液对主井井筒进行地面预注浆。注浆工程竣工后,开挖施工井筒,对整个注浆段剩余涌水量进行实测统计发现:井筒剩余涌水量不足2m3/h,平均堵水率为96.9%,注浆堵水效果显著。 According to the complicated geological conditions and high mine water inrush and other features of Tangkou Mine, a single ce- ment grout and a cement and clay grout were provided for the surface pre-grouting of the mine main shaft. When the grouting operation completed, the excavation and sinking operation was conducted for the mine shaft. A site measurement on the residual water inrush in the full grouted section was conducted and it was found that the residual water value in the mine shaft was not over 2 m3/h and the average wa- ter sealing rate was about 96. 9%. Therefore the grouting water sealing results was obvious.
出处 《煤炭科学技术》 CAS 北大核心 2010年第2期19-21,68,共4页 Coal Science and Technology
基金 新世纪优秀人才支持计划资助项目(NCET-07-0519) 长江学者和创新团队发展计划资助项目(IRT0843)
关键词 注浆堵水 井筒堵水 地面预注浆 唐口煤矿 grouting and water sealing water sealing of mine shaft surface pre-grouting Tangkou Coal Mine
  • 相关文献

参考文献7

  • 1邝键政,昝日稳,王杰,等.岩土注浆理论与工程实例[M].北京:地质出版社,2006:1.
  • 2Цзяо Ви-го Пань Чжун-минь А В Угляница В В,et al.Теория и практика иньекционнгог упрочнения пород в пластовых выработках Угольных шахт[M].Кемерово:Изд КузГТУ.2003:1-15.
  • 3韩立军.岩土加固技术[M].徐州:中国矿业大学出版社,2005.
  • 4刘斌.地下工程特殊施工[M].北京:冶金工业出版社,1991:30-36.
  • 5陈轲,王增光.地面注浆堵水技术在矿山建设中的应用[J].中国矿山工程,2009,38(1):36-40. 被引量:21
  • 6董方庭.井巷设计与施工[M].徐州:中国矿业大学出版社,2004.
  • 7乔卫国,张玉侠,宋晓辉,赵童.水泥浆液在岩体裂隙中的流动沉积机理[J].岩土力学,2004,25(z1):14-16. 被引量:13

二级参考文献3

共引文献83

同被引文献104

引证文献15

二级引证文献83

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部