大伙房水库输水(二期)工程取水口型式独特,结构异常复杂。因工期调整需要,闸墩混凝土浇筑由原计划常规翻升模板改为滑模浇筑,通过技术攻关,高效、优质、安全地完成了取水口闸墩混凝土浇筑任务,压缩直线工期3个月,经济效益显著,为后续项目的施工争取了主动。
The water intake has the unique type and exceptionally complex structure for the water conveyance phase Ⅱ project of Dahuofang reservoir.Because of the time limit modification,the conventional turn up template is changed to slipform pouring for the pier concrete pouring.The pier concrete pouring task of water intake is completed efficiently,high-quality and safely through technical research.The linear time limit is compressed for three months and the economic benefit is remarkable,which leave some leeway for the construction of the follow-up projects.